The total construction area of the composite geomembrane of this reservoir in Honghe Jianshui, Yunnan is 800 square meters. The material used is 1000g composite geomembrane, and the membrane material used is two cloths and one membrane. The total construction time is 1 day. The site is located on the roadside, so it is relatively convenient for the transportation of membrane materials. The power supply is a 3000W gasoline generator. The customer provides 5 auxiliary construction personnel and our company provides 1 construction welding personnel for construction.
This pool is relatively regular in terms of excavation. The size and depth of the entire pool are excavated according to the on-site conditions. There are fewer gravels in the pool. After some treatment, the geomembrane is laid.