The Mengding Wogan planting area in Lincang selected a composite geomembrane with two cloths and one membrane and a thickness of 1000g. The total use area is 2200 square meters, the construction period is 5 days, and the total time from delivery to completion of construction is about 10 days. This is because Mengding is a small border town in Yunnan. It takes about 2 days for logistics to be dispatched from Kunming, and there are also transfers and personnel on the way, so it takes a lot of time.
This construction site is similar to the past. The customer provides the relevant power supply and 4-6 people. We provide 1 technician, and the welding equipment and related auxiliary tools are provided by our company.
For this construction site in Mengding, there are more weathered stones and gravel on the site. Therefore, before construction, we still require a layer of plain soil to be laid on the site, and the sharp stones are de-sharpened, so that even if they are in direct contact with the geomembrane, they will not damage the membrane material.